Landscaping & Hardscaping Chek Lap Kok International Airport
Description
Large-scale grassing works Works performed in 3 phases (1996-1999) Sophisticated logistics were necessary to perform works on the largest work site in the world at this time.
The CLK Airport was being build on an island, partially reclaimed from the sea, offering no fresh water resources, serviced only by ferries, and where hundreds of companies from all over the world were working simultaneously.
Company activity
64 in situ test plots Soil analyses and tests (grass species, conditioners) Installation of an in-situ laboratory
Grassing Method Statement Qulaity Method procedures Assesment and obeservance of a safety plan
Seed bed preparation and soil conditioning
Hydro-seeding over 360 hectares
Soil analysis & tests (grasses, amendments)
In-situ analysis laboratory
Analysis of the results and development of the methodology
Establishment of quality control procedures
Development and implementation of the security plan
Soil preparation and amendment
360 ha of hydro-seeding
Details
Completion date: 1996